Information needed for planning two order releases into a single shiopment

I am working on a scenario, in which i have an order release (wt = 1000 lbs) from "A to B".

A shipment is planned for the same and it is to start at the time, say 04.00 GMT.

Now, I have another order release with the same source, destination and same start time 04.00 GMT.

ORDER RELEASESOURCEDESTINATIONSTART TIMELOAD IN LBSEQUIPMENT CAPACITYEQUIPMENT CAPACITY UTILIZATION1AB04.00 GMT50004000012.5 %2AB04.00 GMT50004000012.5 %

The table above will provide better understanding of the scenario...
If i plan for a shipment, OTM plans a new shipment for order release2.
Equipment utilization is less in both the shipments.

Although it is possible to manually assign order release 2 to the existing shipment from order release1, My query is,

Is there a way to make OTM to check for any shipments with same source, destinations,start time, capacity etc.., and attach the current order release with the existing shipment

Awaiting a response.

Thanks and Regards
Pradeep