Ground Schedule (static route) help needed

Hi,

I have created a simple static route ground schedule with 4 stops. I have also managed to successfully generate 'blank' shipments from this schedule for use in planning.

I have 4 orders which i would like to 'attach' to this blank shipment. If I plan them 'Direct' one at a time then they get succesfully assigned to the statis route.

However if I run a bulk plan on all 4 orders, then a new shipment is created and they do not get assigned to the statis route.

Any ideas why this is as I need to plan all 4 together?

Thanks

Marc