| Re: Key Factors for building a X-Dock / Pooling shipments My advice would be:
1. Take one order and check that without a cross dock on the lane that will build a direct shipment.
2. Take two orders with the same source and destination and make sure they build a direct shipment.
3. Add in a cross dock on the location and make sure that the option via the cross dock is cheaper and feasible (draw out the costs on a piece of paper)
You may need to have both a direct cost and a via cross dock cost in order for OTM to evaluate which is the cheapest.
Re-post if still having issues. |