5.5.03.06 - Change Service Provider after Shipment Events entered


Execution Employing the Tendering process in OTM / G-Log - including the setup of carrier domains, workflow parameters, regional tendering and contact groups.

Reply
 
Submit Tools LinkBack Thread Tools Display Modes
  #1 (permalink)  
Old March 24th, 2009, 03:37
Senior Member and Blogger
 
Join Date: Dec 2006
Location: Singapore
Posts: 179
Blog Entries: 5
Groans: 0
Groaned at 1 Time in 1 Post
Thanks: 6
Thanked 13 Times in 12 Posts
Rep Power: 4
ianlo is on a distinguished road
Send a message via AIM to ianlo Send a message via Skype™ to ianlo
5.5.03.06 - Change Service Provider after Shipment Events entered

Hi everyone,

Does anyone know how to configure OTM to allow the change of service provider on a shipment after events have been captured against it?

As far as I know, Shipment Events can only be entered when the status of
REVIEWED = REVIEWED_EXECUTE and SECURE RESOURCES = SECURE RESOURCES_ACCEPTED.

However setting these two statuses will prevent OTM from allowing you to change the service provider.

Is there a configuration or workaround to allow this?

Thanks!
Ian
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #2 (permalink)  
Old March 24th, 2009, 03:48
Senior Member and Blogger
 
Join Date: Dec 2006
Location: Singapore
Posts: 179
Blog Entries: 5
Groans: 0
Groaned at 1 Time in 1 Post
Thanks: 6
Thanked 13 Times in 12 Posts
Rep Power: 4
ianlo is on a distinguished road
Send a message via AIM to ianlo Send a message via Skype™ to ianlo
Re: 5.5.03.06 - Change Service Provider after Shipment Events entered

Hi,

I think I found a solution. There is a parameter called glog.shipment.event.checkstatus and when set to false, will allow shipment events to be entered without REVIEWED_EXECUTE and SECURE RESOURCES_ACCEPTED.

Hence I can create a shipment, don't tender it, allow it to accept events and change service provider all at the same time.

Hope this helps!
Ian
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Reply


Thread Tools
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On

Similar Threads
Thread Thread Starter Forum Replies Last Post
Cost Difference on Change Service Provider Dropdown Christopher Collins Rating 2 March 9th, 2009 19:05
Changing Service Provider for 1 leg of a Multi-Leg shipment JayVal Planning 1 January 6th, 2009 18:03
Shipment Accessorial from different service provider mramirez Settlement 3 August 18th, 2008 15:01
How to plan a Shipment without any service provider and rates? sandeepdeore Planning 1 August 11th, 2008 16:07
Updating Order Release events when Shipment events are entered vn_karthik Execution 4 January 17th, 2007 20:49



All times are GMT. The time now is 08:22.
Copyright © 2006-2009, Open Book Solutions LLC. All rights reserved.


Inactive Reminders By Icora Web Design

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40