Has anyone worked on "Carrier Commitment Count / Allocation". I enabled the planning parameter " PLAN SHIPMENTS WITH CARRIER COMMITMENT" to true and tried on TL shipments, but still the allocation is not happening.
We have got a lot of problems with the commitment allocation. We have opened a service request with oracle but what they have said till now is that the commitment allocation is not working in two situations:
1-Itineraries that has the option re-use carrier.
2-If you have split orders.
we have the shipment count shown up in the planned part of the commitment usage page , but the finalized section is not getting updated ....also the tables on commitment show no records .. are we missing anything here
Does anyone know how to set up the Commitment Allocation? I am having problems with OTM not showing the Planned Count and Planned Percentage.
PLAN SHIPMENTS WITH CARRIER COMMITMENT planning parameter is set to True.
I set up a commitment allocation for a lane (zip5 to zip5) per the online help instructions
I knew I would need the agent for the Finalized count and percentage. I found an issue when looking at my log files. there was a very large set of X_lane records to evaluate when OTM tried to record the plan counts. Once I removed the (old rate records) x_lanes, the planned count worked.