Old June 25th, 2008, 08:22
Junior Member
 
Join Date: May 2008
Posts: 4
Thanks: 0
Thanked 0 Times in 0 Posts
Groans: 0
Groaned at 0 Times in 0 Posts
Rep Power: 0
pmalin is on a distinguished road
consolidation + deconsolidation scenario

Need to make such scenario, but itinerary cant has both consolidation and deconsolidation.

from A to F
from B to F
from C to G

I successfully did consolidation and delivery to E, but when try to make deconsolidation planning fails with error
Quote:
Itinerary {1=null} has both consolidation and deconsolidation checked
Have any ideas to realize this?
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #2 (permalink)  
Old August 21st, 2008, 18:37
Member
 
Join Date: May 2007
Posts: 89
Thanks: 16
Thanked 1 Time in 1 Post
Groans: 0
Groaned at 0 Times in 0 Posts
Rep Power: 2
rj5316 is on a distinguished road
Re: consolidation + deconsolidation scenario

Hi,

can u share the setups you did for conslidated load to be delivered to E...

Appriciate ur help..

Rgds-
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #3 (permalink)  
Old August 22nd, 2008, 13:01
Junior Member
 
Join Date: Apr 2007
Posts: 14
Thanks: 0
Thanked 0 Times in 0 Posts
Groans: 0
Groaned at 0 Times in 0 Posts
Rep Power: 0
salsharm is on a distinguished road
Re: consolidation + deconsolidation scenario

I successfully configured a very similar scenario some time back. Consolidation and Deconsolidation together. If you provide more details, I will try to see what is going wring.

Regards,
-Salil
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #4 (permalink)  
Old August 27th, 2008, 05:30
Member
 
Join Date: May 2007
Posts: 89
Thanks: 16
Thanked 1 Time in 1 Post
Groans: 0
Groaned at 0 Times in 0 Posts
Rep Power: 2
rj5316 is on a distinguished road
Re: consolidation + deconsolidation scenario

Hi,

we are trying a simple deconsolidation scenario:

2 order releases going on a TL shipment to a deconsolidation location and then getting split into 2 LTL shipments . I.e common source but diff destinations... On using the bulk plan OTM creates 2 TL shipments form the origin instead of one TL... we have raised a SR for this... but have not got any firm solutions on this....we are on CU 4...

rgds--
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #5 (permalink)  
Old August 28th, 2008, 06:35
Member
 
Join Date: May 2007
Posts: 89
Thanks: 16
Thanked 1 Time in 1 Post
Groans: 0
Groaned at 0 Times in 0 Posts
Rep Power: 2
rj5316 is on a distinguished road
Re: consolidation + deconsolidation scenario



hi we were able to solve this ... (may be a work around).....by assigning a cross dock role to the loctaion, which as per the help file / core comp should function as a deconsol pool....

the same scenario (i.e 1 TL and 2 subsequent LTLs) works with a deconsol role in cu2 / 3 and as a x dock in cu 4. If we use a deconsol role in cu 04 we get 2TLs and 2 LTLs.... ?

we have raised a SR for this ....

In the meanwhile any help .. suggestions wuld be welcome.... or if any one can share how they have used a deconsol location role in cu 04, it would also be of gr8 help to understand the above issue

rgds--
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #6 (permalink)  
Old September 1st, 2008, 13:08
Member
 
Join Date: May 2007
Posts: 89
Thanks: 16
Thanked 1 Time in 1 Post
Groans: 0
Groaned at 0 Times in 0 Posts
Rep Power: 2
rj5316 is on a distinguished road
Re: consolidation + deconsolidation scenario

Hi,

Just got an update from oracle that the issue has been registered as a BUG ID 7217620 and would be resolved in 5.5 CU 5 roll up 3 which is due in jan 09....

lets keep our fingures crossed..!!

Rgds--
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Reply



Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On

Similar Threads
Thread Thread Starter Forum Replies Last Post
Consolidation Pool cool_brat Planning 3 May 29th, 2008 21:11
[SOLVED] MultiStop Scenario cool_brat Planning 17 May 23rd, 2008 07:46
Consolidation / Deconsolidation and Cross Docking Scenarios ! ragsridh Planning 5 December 17th, 2007 08:06
Problem - Notifications - CONSOLIDATION PROFILE Sanju Workflow 0 September 12th, 2007 08:47
Consolidation orders using itineraries Brian.Hogue Planning 3 December 14th, 2006 22:08



All times are GMT. The time now is 04:12.
Copyright © 2008, Open Book Solutions LLC. All rights reserved.

Sponsored by MavenWire - MavenWire.com


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37