Planning Planning orders in OTM / G-Log - including bulk planning, itineraries, planning parameters, load configuration and optimization.

Tags: ,

Reply
 
Submit Tools LinkBack Thread Tools Display Modes
  #1 (permalink)  
Old March 15th, 2007, 12:02
Junior Member
 
Join Date: Mar 2007
Posts: 1
Thanks: 2
Thanked 0 Times in 0 Posts
Groans: 1
Groaned at 0 Times in 0 Posts
Rep Power: 0
harrycrumb is on a distinguished road
Arrow Turn Off Planning Module

Is there a way to turn off the complete planning Module of OTM? I amcurrently working on OTMv 4.5
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #2 (permalink)  
Old March 21st, 2007, 17:52
Junior Member
 
Join Date: Dec 2006
Location: Holly Springs, NC
Posts: 19
Thanks: 0
Thanked 1 Time in 1 Post
Groans: 0
Groaned at 1 Time in 1 Post
Rep Power: 0
JoeMac is on a distinguished road
There's no button where you would turn something on or off in OTM. If you design a process that does not invoke planning to build a shipment then you do not have to worry about an order getting planned. This will require you to create shipments manually or via integration and you also lose a valuable tool in the process. But you're not forced to use OTM's planning algorithm by any means.
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
The Following User Says NO Thank You to JoeMac For This Un-useful Post:
harrycrumb (August 8th, 2008)
  #3 (permalink)  
Old March 23rd, 2007, 08:24
Junior Member
 
Join Date: Mar 2007
Posts: 11
Thanks: 0
Thanked 5 Times in 4 Posts
Groans: 0
Groaned at 0 Times in 0 Posts
Rep Power: 0
andyp222 is on a distinguished road
In this case the issue is that there is a significant processing overhead during the loading of TransOrder's via XML associated with planning, e.g. looking for substitute locations and refreshing the Order Release Cache. A very high volume of orders need to be loaded each day with complex Agents, so getting ,maximum performance is key.
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
The Following User Says Thank You to andyp222 For This Useful Post:
harrycrumb (August 8th, 2008)
Reply



Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On

Similar Threads
Thread Thread Starter Forum Replies Last Post
Planning Parameters and Multi-Stop Planning Rates joecallan Planning 3 May 23rd, 2008 06:36
Planning parameters and properties in v5.5 to improve Bulk Planning sknmail@rediffmail.com Performance, Scalability and HA 5 April 25th, 2008 14:30
Need to turn off PASV ftp acuartero Integration and Data Mapping 2 January 8th, 2008 18:11



All times are GMT. The time now is 18:20.
Copyright © 2008, Open Book Solutions LLC. All rights reserved.

Sponsored by MavenWire - MavenWire.com


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37