Thanks: 3
Thanked 5 Times in 5 Posts
Groans: 0
Groaned at 0 Times in 0 Posts
Rep Power: 0
cwarner is on a distinguished road
Unexplained planning behavior

We are having some strange behavior in our systems. Let me start by giving a bit of background.

We have three environments. Production (5.5 CU2), Training (5.5 CU2), and Development (5.5 CU3). We wanted to use conditional booking on our TL's so that we could get dates from the trucker of when he would pickup and deliver the load. This is only an issue if loads had 3 or more stops on them.

When we setup this in our first environment, we noticed that the middle stops were not replanned to fall between our start and end dates. To resolve this issue, we added some steps to an agent that would update the Estimated Arrival and Departure times of the first stop, which would then replan the second stop. We could then back out the changes to the first stop without the second stop reverting. This fixed our issue with 3 stop loads.

When we moved this live in our production environment (we had waited about a month before moving it live) we did not see the same behavior . Production was not replanning the second stop when the Estimated Arrival and Departure were updated. The first thing we did was we went back to our training and development environments, and found that now they weren't replanning the second stop either.

Bewildered and discouraged we were unable to find what had changed, and learned to accept the fact that we needed to function differently now with multistop loads.

Yesterday alarmed me. I discovered that both Training and Development are again replanning the second stop, although it is not currently happening in production.

The only thing that I see the same was that we modified planning parameters in both of the windows of change, however the parameters that we changed have absolutely nothing to do with dates or times, but have to do with weights of the shipment. How could this change that?

I am now concerned that our production environment could change on us as the other two environments have. We have compared saved queries, agents, and planning parameters, and have yet to discover any differences between our environments that could have done this.

Where should I look to find these differences? Does anyone have any idea what might be going on? Any help you could offer would be wonderful. Thank you.

Caleb

Last edited by cwarner : January 17th, 2008 at 14:45.
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #2 (permalink)  
Old January 23rd, 2008, 15:45
Member
 
Join Date: Sep 2007
Posts: 39
Thanks: 3
Thanked 5 Times in 5 Posts
Groans: 0
Groaned at 0 Times in 0 Posts
Rep Power: 0
cwarner is on a distinguished road
Re: Unexplained planning behavior

Well, since we couldn't figure out what was causing the difference between our environments, we have scheduled a clone from production to over top of our training environment for tomorrow morning. Hopefully our inconsistancies will go away after this.
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Reply



Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On

Similar Threads
Thread Thread Starter Forum Replies Last Post
Planning Parameters and Multi-Stop Planning Rates joecallan Planning 3 May 23rd, 2008 06:36
Planning parameters and properties in v5.5 to improve Bulk Planning sknmail@rediffmail.com Performance, Scalability and HA 5 April 25th, 2008 14:30



All times are GMT. The time now is 11:46.
Copyright © 2008, Open Book Solutions LLC. All rights reserved.

Sponsored by MavenWire - MavenWire.com


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36