| Re: X-dock deconsolidation Hi Karthik,
For the case mentioned above. What are the Rate Offerings that you have created?
What i would suggest is to have 3 Rate offerings
1. From A to B (TL rate offering type)
2. From B to the Destination Region (put C& D in one region) create LTL Rate Offfering type
3. Handling Rate Offering for B which is the De consolidation point.
Try planning again after doing the above setup.
If it still does not work what you can try next is, modify you itinerary.
Instead of Multi-leg what you can do is check the "Deconsolidation Pool" check box and also the "Match Deconsol Pool To Dest" check box in the itinerary parameters tab. and create itinerary from Source A to Destination region.
Let me know if this works.
Regards,
Divya |