  #1 (permalink)  
Old March 9th, 2009, 19:17
Member
 
Join Date: Jun 2008
Posts: 64
Groans: 0
Groaned at 0 Times in 0 Posts
Thanks: 5
Thanked 3 Times in 3 Posts
Rep Power: 2
Christopher Collins is on a distinguished road
Deconsolidation Pool Selection

We have a set-up which includes deconsolidation pools with overlapping regions.

We are having a problem with the system choosing a pool that doesn't have a rate to the particular location we are going to even though the deconsolidation pool has the location in the region.

I can't find any restrictions, but can anyone confirm if the system cannot handle overlapping deconsolidation pool regions?

Thanks,

Chris
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #2 (permalink)  
Old April 2nd, 2009, 05:43
Senior Member
 
Join Date: Sep 2007
Location: india
Posts: 182
Groans: 0
Groaned at 0 Times in 0 Posts
Thanks: 7
Thanked 13 Times in 13 Posts
Rep Power: 3
nipunlakhotia is on a distinguished road
Send a message via Yahoo to nipunlakhotia
Re: Deconsolidation Pool Selection

Hi Chris,

As per OTM planning engine algorithm, each location should be linked to one pool only i.e. pools with overlapping regions should not be configured.

OTM planning engine determine the routing for shipments based on itineraries. If pool is mentioned in itinerary, then it will look for applicable pool location regardless of rates. Once pool location is determined, then it look for valid rates to create shipments. Thus selection of pool is independent of rates availble in the system.

In case there are more than one pool applicable for a given lane i.e. pools with overlapping regions, OTM selects any one of them regardless of rates.
__________________
Regards,
Nipun Lakhotia
OTM Center of Excellence, Infosys
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Reply


Thread Tools
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On

Similar Threads
Thread Thread Starter Forum Replies Last Post
Selection of Equipment using Temp_Control_ID Sanju Planning 5 September 14th, 2009 09:24
X-dock deconsolidation karthiktc Planning 1 March 6th, 2009 05:04
Service Provider Profile Use for Itinerary or Rate Record Selection sboro Rating 2 December 26th, 2008 20:01
consolidation + deconsolidation scenario pmalin Planning 5 September 1st, 2008 12:08
Multistop Deconsolidation scenario arunk Planning 4 August 21st, 2008 04:39



All times are GMT. The time now is 21:53.
Copyright © 2006-2009, Open Book Solutions LLC. All rights reserved.


Inactive Reminders By Icora Web Design

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40